Ayley Croft, Jeremys Green, Masons Road, the Avenue Estate and Cedars Court could take 260 council-led homes. Scrutiny councillors discuss it on 25 November.
Overview
Enfield Council has named five pieces of its own housing land as the first batch for new homes under its small sites plan. Together they could take about 260 homes. The sites are Ayley Croft, Jeremys Green, Masons Road, the Avenue Estate and Cedars Court. Councillors on the Housing and Regeneration Scrutiny Panel discuss the plan on Wednesday 25 November.
The list is in a Small Sites and SME Update written for the panel by the council’s Director of Development and Property. The numbers are indicative. Officers say each site is still going through feasibility, capacity and viability checks.
The first five sites
The report gives these indicative figures:
| Site | Homes |
|---|---|
| Ayley Croft | 80 |
| Jeremys Green | 58 |
| Masons Road | 51 |
| Avenue Estate | 50 |
| Cedars Court | 21 |
| Total | 260 |
The report does not say what is on each site now or exactly where on each estate the homes would go. It describes the wider programme as mostly infill, garage sites, conversions and small brownfield plots.
The council wants to offer these sites to small and medium-sized builders and housing associations. Officers will then rank sites by how many homes they give, how affordable and deliverable they are, and their planning risk. A first tranche then goes for formal approval. No date for that is given.
The bigger list behind it
The five come from a longer list of council land. The report says up to 44 council sites are under consideration, which could hold between 800 and 1,500 homes. Their sizes break down like this:
- 13 sites with room for up to 10 homes
- 19 sites for between 12 and 30 homes
- 11 sites for between 32 and 70 homes
- 4 sites for between 75 and 80 homes
A separate Housing Delivery and Brownfield Sites Update for the same meeting says a borough-wide review of council estate land produced 50 potential infill sites. It puts the capacity of the council’s brownfield housing land at around 3,000 affordable homes.
Chasing 52 stalled schemes
The plan also targets private sites that already have planning permission for 20 homes or fewer but have not been built. The council found 52 of them, with room for about 350 homes:
- 30 stalled or lapsed schemes, about 200 homes
- 22 live schemes, about 150 homes
Officers say they have contacted all 52 developers and landowners. Seven have sent detailed replies so far. The report says viability is “the single biggest challenge”, pointing to building costs, finance and market uncertainty. The council plans an event for small builders and landowners in the new year.
Where the bigger schemes stand
The brownfield report says 651 homes are being built on council schemes now. It gives this progress:
- Joyce and Snells, Upper Edmonton: main works have started on Block A, with 50 homes. The whole scheme is planned at 2,028 homes, at least half of them affordable.
- Upton and Raynham, off Fore Street: 135 affordable homes, due to be finished in 2028.
- Dendridge Close, Bullsmoor: 27 homes on two former garage sites, built over 24 months from January 2026.
- New Avenue: the council is buying 159 homes that were to be sold privately, to let at social rent. First homes in that final phase are due in 2029.
The report says the programme has secured more than £280 million of grant funding so far.
What it means for you
- If you live on one of the five estates, nothing has been decided. Each site still needs design work, a viability check, council approval and planning permission. Any building would need a planning application you can comment on.
- The scrutiny panel meets at 7pm on Wednesday 25 November. The meeting page has the agenda and both reports. Scrutiny panels comment and question; they do not make the decision.
- If you own a site with planning permission that has stalled, the council says it has a dedicated officer as a single point of contact for developers, agents and landowners.