The Ridgeway data centre would have 72 back-up generators, and its grid upgrade is not due until 2033. Orbital has asked Enfield Council to rule on its study.
The data centre planned beside Junction 24 of the M25 would have 72 back-up generators and buildings up to 29 metres tall in places. The electricity upgrade it depends on is not due to be finished until October 2033.
The figures are in a 133-page report that Orbital Data Centres has sent to Enfield Council. The council logged it on 9 November as a formal request for a “scoping opinion” (reference 26/04732/SCOP). That is the council’s ruling on what the developer’s environmental study has to cover before it applies for planning permission. (Enfield Council planning record, 26/04732/SCOP)
The same report has gone to Hertsmere Borough Council, because the site straddles the border with Potters Bar.
What the report adds
Orbital’s public consultation, which we reported last month, gave the outline: two buildings, about 50,000 square metres of floorspace, on Green Belt farmland between The Ridgeway and the motorway. The scoping report gives the detail: (Environmental Impact Assessment Scoping Report, Lawson Planning Partnership, November 2026)
- 72 back-up generators, to run if the National Grid supply fails and otherwise only for routine testing and maintenance
- a grid connection of up to 150 megawatts, agreed with UK Power Networks, with the network upgrades “programmed for completion by 31 October 2033”
- an IT load of 108 megawatts, which the report says it will reconcile with the 150 megawatt connection later
- buildings 22 metres high plus 3 metre flues, which could reach up to 29 metres above today’s ground level in places, because the land slopes
- earthworks cutting up to about 3.3 metres into the western field and raising the eastern one by up to about 6.8 metres
- the removal of the pylons that cross the site, with the cables put underground or diverted
The report describes it as an “AI and Cloud Data Centre”. The application would be in outline, with only the access fixed at first. The look and layout would come later.
The site in the report is 12.17 hectares, about 30 acres. That is a little larger than the 11.65 hectares on the consultation website. It includes 501 New Cottage, a house on The Ridgeway that was converted into four flats under a 2018 permission.
Three years of building
Orbital expects construction to take about three years. The report’s transport section estimates:
| Construction measure | Report’s estimate |
|---|---|
| Most construction staff on site at once | 800 |
| Daily vehicle movements at the peak, worst case | about 1,660 |
| Lorry movements a day at the peak, over about 8 months | about 60 |
| Concrete lorry movements a day while foundations are poured | up to 100 |
| Water tanker deliveries to fill the cooling system | up to 45, over nine weeks |
The report expects most lorries to use Junction 24 and The Ridgeway west of the site. It says the extra traffic would add less than 10% to daily flows on local roads. Work would normally run from 8am to 6pm on weekdays, with Saturday mornings only if needed and no Sunday working.
Once open, it expects about 175 trips a day to and from the site, 170 by car and five by lorry. Most staff would arrive and leave at shift changes at 6am, 2pm and 10pm, outside the rush hours.
What the developer wants studied, and what it does not
Orbital accepts that the scheme needs a full environmental impact assessment. It proposes that only two subjects get a full chapter:
- climate change, including the carbon from building and running the site
- landscape and the view of the buildings from around the site
It proposes leaving the rest out of the formal study as stand-alone chapters, including:
- air quality
- noise
- traffic
- water and flooding
- wildlife
- heritage
It says each would still be covered by a separate technical report with the application. The generators’ fumes, for example, would be modelled in an air quality report.
The council now decides whether it agrees. Its scoping opinion can add subjects the developer left out.
The Local Plan fight
In June, the inspector examining Enfield’s draft Local Plan told the council to delete this land’s allocation for industry, site RUR.04, and keep it in the Green Belt. (Inspector’s letter IN14, paragraphs 73 to 78)
The scoping report says Orbital’s planning consultants will push back. They “will be submitting robust representations” when the council consults on the plan’s changes. They will argue the plan “would not be unsound” if the allocation stayed in a revised form.
The report also says Enfield Council still owns the land. Orbital, it says, has “exchanged signed contracts, with a completion date agreed”. Orbital’s consultation website says it bought the site in January. The council’s own decision record shows Cabinet agreed the sale in January. (Enfield Council decision record, KD 5974)
The report also says Orbital is entering a joint planning performance agreement with Enfield and Hertsmere. That is an agreement with both councils on how the scheme is handled before an application goes in.
What it means for you
This is not yet a planning application, so there is no formal objection stage at the council. That comes when the outline application is lodged, and both councils will consult then.
You can still comment to the developer. Orbital’s own consultation closes on Sunday 22 November, through the feedback form on the consultation website, by email to consultation@realestatecomms.com or by phone on 07523 696293.
The scoping report is public on the council’s planning portal under 26/04732/SCOP, and anyone can read it there. The council’s scoping opinion will be published under the same reference.